Pravaha site plan — 12-lot subdivision at 1-21 Nash Court, Caboolture
1–21 Nash Court
Caboolture · QLD
Delivery project · Client-owned

Finishing what another developer left behind.

A stalled 12-lot subdivision, rescued and being delivered by SAI Holdings on behalf of the new landowners.

The takeover

Every lot already sold.

The original developer completed Stage 1 (Lots 1–7 & Lot 900 stormwater drainage reserve) and walked off site — leaving the balance stages unfinished and buyers waiting. When the new landowners took over, they authorised SAI Holdings to take charge of the project and deliver the outstanding Stages 2A and 2B. Every one of the 12 lots is already sold. The site is currently with Energex for the final electrical works required before plan sealing — after which titles issue to buyers and the project is closed out.

12 Total lots All sold
7 Stage 1 lots Complete
5 + balance Stages 2A & 2B SAI Holdings scope
1.9 ha Overall area Moreton Bay Regional Council
Our scope on Pravaha

A takeover, executed cleanly.

01

Rescued a stalled project

The original developer completed Stage 1 and walked off site. New landowners authorised SAI Holdings to step in, take over the works and see the balance stages through to sealing.

02

Council & authority management

Coordinating Moreton Bay Regional Council, ARC Surveys and Energex on the reconfiguration of Lot 201 on SP169503 into Lots 1–12, 500 (balance) and Lot 900 (stormwater drainage reserve).

03

Delivering Stages 2A & 2B

Balance civil works, service connections and compliance sign-offs for the remaining 5 lots plus the balance lot — engineered to finish what was left behind.

04

Awaiting Energex sign-off

All lots are sold. The project is now with Energex for final electrical works before plan sealing and title issue to buyers.

The site plan

Twelve lots on Nash Court.

Pravaha site plan showing Lots 1-12, the balance lot 500 and Lot 900 stormwater drainage reserve

Site plan issued by ARC Surveys Pty Ltd · Plan 1674PP Rev C.

Stalled project?

Have a stalled project? We take over.

SAI Holdings steps into projects that need experienced hands — from council coordination through to plan sealing and title.